Avalanche of interruptions and stack sizes
Rafael Morales
rmorales at iaa.es
Thu Aug 28 06:28:00 UTC 2014
Dear all,
I'm working with Leon3 at 25Mhz, RTEMS 4.10 and a list of devices that
generates interruptions.
Nominally, there are 18 tasks running and the program is stable, but at
certain time, one of the devices generates an avalanche of interruptions
and the program stops suddenly.
The only way to stabilize program in is to increase the BSP stack (If
I'm not wrong it also increases the ISR and task stack).
But, why?, Which is the effect of a avalanche of interruption in the
stack size?
Any idea?
Thanks in advance.